Installing a Fixed Cat Ladder on an Existing Building

Design the complete access route and apply the exact regulatory thresholds, practicability wording and project approval route.

Flowchart: measure the whole route from approach to roof, including supports, landings, obstructions, users, tools and the final destination. First decision: are the regulation 18 route checks resolved? If no, design and measure further because the route or approvals are unresolved. Second decision: is the installed work reconciled with the design? If no, do not release it because inspection evidence is outstanding. If both are yes, retain the compliance basis: at least a 1 metre extension or adequate handhold, landings where practicable on runs over 9 metres with no more than 9 metres between landings and guards, a cage or other practicable fall prevention on rises over 3 metres, and access control with future inspection.
Fixed-ladder flow: verify the route, regulation 18 thresholds and installation evidence before release. Preserve the one-metre/handhold, over-9 m landing and over-3 m fall-prevention requirements. Swipe sideways to read it, or open the full-size flowchart.

Brief the route from approach to destination

Provide levels, intended users, frequency, photographs and available structural and roof drawings. Mark beams, parapets, plant, services, openings and obstructions. Explain whether users carry tools or bulky items and how they approach the ladder, step across any landing, pass through the roof transition and continue to the work area.

Agree what must be measured or opened up before fabrication and how discrepancies in the existing structure will be escalated. A ladder detail cannot be assessed properly without its support, landings and final destination.

Use the regulation 18 thresholds accurately

Regulation 18 requires at least a one-metre ladder extension or an adequate handhold above the landing place or the highest rung to be reached by the user’s feet, as applicable. For a fixed vertical ladder or run rising over 9 metres, it requires an intermediate landing where practicable, with no more than 9 metres between successive landings, and guard-rails or barriers at those landings. [1]

For a fixed vertical ladder rising more than 3 metres, regulation 18 requires a safety cage or other practicable fall-prevention measures. A cage is therefore not the only possible solution. The designer should assess the complete route and select compliant, suitable measures rather than treating one dimension or device as a universal design.

Resolve approvals and handover before release

Ask the design professional to determine whether structural plans or other approval are required, or whether a specific exemption applies. BCA publishes separate guidance on structural plan submission and building works not requiring approval. Exemption from one approval route is not proof of structural adequacy or compliance with workplace duties. [2] [3]

Before use, reconcile the installed work with the design and required inspections, and establish access control, user briefing and future inspection arrangements. Keep the approved or accepted drawings, verification records, unresolved limitations and maintenance instructions with the asset.

Related: see our roof access and cat ladder support.

For cat ladder design, fabrication and installation, see Metal Singapore, our sister site for metal works.

Read next: Roof Access and Cat Ladder Safety Singapore.

Practical checklist

  • Assess approach, support, landing, roof transition and destination together.
  • Preserve the exact more-than-3 m and over-9 m wording and practicability qualifiers.
  • Let the design professional determine submission or exemption status.
  • Do not release the route until installation verification and future inspection arrangements are recorded.

References

  1. Workplace Safety and Health (Work at Heights) Regulations 2013 (Singapore), reg. 18. Singapore Statutes Online.
  2. Building and Construction Authority. (n.d.). Structural plan submission.
  3. Building and Construction Authority. (n.d.). Building works not requiring approval.